Migrating a data platform between vendors — without the business feeling it.

A legacy SaaS platform was being retired and the business was moving to a new vendor system. I owned the migration — mapping ~20 business objects and 300+ fields source-to-target on Google Cloud, reconciling every record before cutover, and running the vendor and change management — so the switch landed with zero disruption to live operations.

Case Study Snapshotproblem → solution · at a glance
The problem
  • A business-critical SaaS platform was reaching end-of-life.
  • Its data had to land in a new vendor platform with different schema.
  • Live operating cycles — transactions, approvals, payouts — couldn't stop.
  • One mismapped field would silently corrupt downstream reporting.
What I did
  • Classified it as Repurchase + Retire; ran it phased + parallel.
  • Built the source-to-target field map — the vendor's build contract.
  • Reconciled every object in BigQuery behind a go/no-go gate.
  • Armed a rollback path before every wave went live.
Google CloudBigQuerySQLSource-to-target mappingData reconciliationVendor managementChange managementCutover & rollback

Scope & strategy

A vendor-to-vendor platform migration — scoped, mapped, and reconciled end to end.

~20
Business objects mapped
Accounts, contacts, opportunities, transactions, activity, plus reference data — each with a defined target.
~60
Tables migrated
Core, reference, staging and mapping tables moved and validated across the estate.
300+
Fields source-to-target
Every field mapped with a transform rule and a validation gate in the mapping document.
Zero
Downtime at cutover
Phased with a parallel run, so live operating cycles never stopped.
Migration profileRepurchase + Retire · phased + parallel run · ~20 objects / ~60 tables / 300+ fields · ~5 integrated systems (CRM, ERP, warehouse, BI) · Google Cloud (BigQuery)

The migration, end to end

From the retiring platform to the live one

One picture of the whole thing: the legacy platform's data flows through a BigQuery engine that maps, transforms, matches, and reconciles it — and nothing crosses into the new platform until parity passes.

Artifact · Migration architecturelegacy → BigQuery engine → new platform
LEGACY PLATFORM being retired Accounts · Contacts Deals · Transactions Activity · Reference ~20 objects / ~60 tables GOOGLE CLOUD · BIGQUERY ENGINE 1 Map source → target field map 2 Transform value maps · currency · dates 3 Match golden record — dedupe accounts 4 Reconcile source ↔ target parity ✓ PARITY GATE — GO / NO-GO NEW PLATFORM live Mapped schema Reconciled data Business running ✓ zero downtime ROLLBACK · PARALLEL RUN (legacy read-only)

The legacy system stays live and read-only in parallel (the amber path) — so any wave can be rolled back cleanly until the new platform has proven itself.

What kind of migration — and why

Not a server move. A vendor swap.

This wasn't lifting infrastructure to the cloud. The incumbent SaaS platform was being sunset by the vendor, and the business had chosen a replacement product. The data had to move from one vendor's schema to a completely different one — while the business kept operating on it. Three things made it hard:

Two schemas that disagree

Different field names, types, code values, and grain. Nothing mapped one-to-one — every field needed a rule.

Live cycles couldn't stop

Transactions, approvals, and payouts were in flight. A hard switch would freeze the business, so downtime had to be effectively zero.

Integrity is non-negotiable

The platform fed CRM, ERP, warehouse, and BI. One mismapped field would silently corrupt everything downstream.

Choosing the strategy

The 7 Rs — which one, and why

Before touching data, I classified the move against the industry-standard 7 Rs of migration. Naming the strategy up front is what turns a data project into a governed migration — it sets the plan, the risks, and the exit criteria.

Decision · 7 Rs assessmentstrategy · when to use · fit here
StrategyWhen you use itFit here
RehostLift-and-shift infrastructure as-is to new hosting.No — there's no server to move; the platform is vendor SaaS.
ReplatformMove with light optimization in flight.No — not a re-hosting exercise.
RefactorRe-architect an application you own.No — we don't own the app; it's a vendor product.
RepurchaseRetire the tool and adopt a new SaaS product (drop-and-shop).Yes — the business moved to a new vendor platform.
RetireDecommission what's redundant or end-of-life.Yes — the legacy platform and duplicate objects were retired at cutover.
RetainKeep on the current platform for now.No — vendor end-of-life forced the move.
RelocateMove VM workloads (e.g. VMware) to cloud.No — not a VM workload.

The call — Repurchase + Retire

The incumbent was being sunset and a replacement product was already chosen, so Repurchase was the only honest classification — paired with Retire for the legacy system and its redundant data. That framing set everything downstream: the work was a data migration into a purchased product, so success hinged on the source-to-target mapping and reconciliation, not on re-architecting anything.

Strategy locked: Repurchase + Retire, executed phased with a parallel run.

How to cut over

Big bang, phased, or parallel?

Strategy answers what; execution answers how you flip the switch. With live cycles running, the execution model was the real risk decision.

Execution optionsapproach · trade-off · decision
ApproachWhat it isDecision
Big bangMove everything in one cutover window.Rejected — live cycles would freeze, and one failure means a total rollback.
PhasedMigrate in object-group waves, each with its own QA and reconciliation.Chosen — contains blast radius; each wave proven before the next.
Parallel runOld and new run together; legacy kept read-only through hypercare.Chosen — zero downtime, and a clean backout if parity fails.

The cutover loop, per wave

Every object-group wave ran the same governed loop — and only a parity pass earned a go-live.

Artifact · Cutover flowchartmigrate → reconcile → go / no-go
Migrate wave one object group Reconcile parity rows & control totals Parity pass? PASS Go-live · cut over next wave → repeat until legacy retired FAIL Rollback via parallel run Fix mapping with the vendor
Why phased + parallel

The business could not pause. A phased wave plan let me reconcile each object group in isolation, and a parallel run kept the legacy system available (read-only) as the rollback path until the new platform had proven itself. Slower than a big bang — but the only responsible choice when payments and approvals are live.

The governance spine

Four quality gates — nothing advances until the prior one passes

The migration ran on a standard assess → design → implement → validate lifecycle with hard gates. That is what makes a migration auditable instead of hopeful.

Artifact · The four quality gatesno gate skipped
Gate 1 · Assess
Inventory & discovery complete. Every object, table, dependency and owner catalogued; the source-to-target map signed off with business definitions.
Gate 2 · Design
Transforms built & unit-tested. Value maps, currency and date conversions, and golden-record matching — proven against sample data.
Gate 3 · Reconcile
Parity proven. Row counts and control totals tie out per object group; exceptions routed to a queue, not ignored.
Gate 4 · Cutover
Go / No-Go. Decision against pre-defined thresholds; parallel run and rollback plan armed; business sign-off before the wave goes live.

Discovery & inventory

The source-to-target map — the document that is the migration

Every field, from the legacy schema to the new one, with a transform rule and a validation gate. This single artifact reconciled three things at once — the old schema, the new schema, and what the data means to the business — and it was the contract the vendor built against.

Why this artifact

A migration fails in the gaps between "what the old system stored" and "what the new system expects." Writing every field down — with a rule and a check — is what turns those gaps from production incidents into review-desk decisions.

Artifact · Source-to-target field map (representative)legacy → new · rule · gate
Source (legacy)Target (new)Transform / ruleValidation gate
opportunity_iddeal_idDirect copyNot null, unique (primary key)
account_nameaccount_idGolden-record match to CRM master; similarity ≥ 0.92100% resolved or exception queue
amountamount_usdConvert to USD via fx_rate on close_dateΣ(source) = Σ(target) within ±0.5%
statusstage_codeValue-map lookup (enum)No orphan or unknown codes
created_ts (UTC)created_dateCast UTC timestamp to reporting-timezone dateDate-shift / off-by-one audit
region_stringregion_id + subregion_idSplit delimited string + reference lookupReferential integrity, no nulls

Field and table names are representative of the method, not any employer's schema. The real map ran to 300+ fields across ~20 objects — the discipline of a rule and a gate on every field is the point.

The build — hands-on GCP

Reconciliation is the gate that makes it trustworthy

The parity check below is the go/no-go — it compares source and target by object group, and a clean run returns zero rows.

Artifact · BigQuery reconciliation (parity gate)source ↔ target · returns only mismatches
-- Row-count + control-total parity by stage; a clean run returns 0 rows
WITH src AS (
  SELECT status AS stage, COUNT(*) rows, SUM(amount_usd) amt
  FROM `legacy_platform.opportunity`
  WHERE _ingest_date = @cutover_date
  GROUP BY status
),
tgt AS (
  SELECT stage_code AS stage, COUNT(*) rows, SUM(amount_usd) amt
  FROM `new_platform.deal`
  WHERE load_date = @cutover_date
  GROUP BY stage_code
)
SELECT
  COALESCE(s.stage, t.stage)                          AS stage,
  s.rows, t.rows, s.rows - t.rows                       AS row_delta,
  ROUND(SAFE_DIVIDE(ABS(s.amt - t.amt), s.amt)*100, 2) AS amt_pct_delta
FROM src s
FULL OUTER JOIN tgt t USING (stage)
WHERE s.rows != t.rows OR ABS(s.amt - t.amt) > 1;

The same suite also ran, per wave:

Every check had to pass to clear Gate 3.

Contingency & rollback

Plan the backout before you need it

Rollback isn't a panic move — it's a decision made calmly, in advance, against numbers agreed before go-live.

Triggers set up front

Rollback thresholds were defined before cutover — measurable conditions (parity failures, blocked cycles) that flip a wave from go to no-go, decided cold rather than mid-incident.

A live backout path

The parallel run kept the legacy system read-only through hypercare, so reverting a wave was a known, rehearsed operation — not a scramble.

Mock cutover + exceptions

A dry run tested timing and coordination; unresolved records went to an exception queue with an owner, never into the target unvalidated.

Vendor & change management

Holding two vendors and the business through the switch

A vendor migration is as much a people problem as a data one: an incoming vendor building to spec, an outgoing platform being retired, and a business that has to keep trusting its numbers throughout.

The vendor gate I held

The field map was the contract the incoming vendor built against. In mapping review I found a source field with no clean target that would have silently corrupted downstream data — I escalated it, held the go-live gate until the vendor closed it, and only then reconciled and cut over. The vendor built to one agreed spec instead of guessing.

Change management · how I ran the transitioncadence · stakeholders · trust
DimensionHow I ran it
WavesSequenced into object-group waves — each mapped, reconciled, and signed off before the next — so risk stayed contained and progress stayed visible.
StakeholdersKept business, data/IT, finance, and the vendor implementation team aligned to one plan and one field map — a single source of truth for what was moving and when.
Comms & adoptionTold affected teams what changed, when, and what to check — so the new platform's numbers were trusted from day one, not second-guessed.
TrustMade reconciliation visible: the same control totals reconciled on both systems, so no one had to take the migration on faith.

Outcome

The switch nobody had to feel

The measure of a good migration is that the business barely noticed it happened — the data was simply there, correct, in the new system.

Zero disruption

Phased waves and a parallel run meant live operating cycles kept running throughout — no freeze, no downtime window imposed on the business.

Reconciled at cutover

Every object group passed source-to-target parity before it went live; nothing crossed on faith, and there was a rehearsed backout if it hadn't.

A clean retirement

The legacy platform was retired on schedule with its data fully accounted for — the point of a Repurchase + Retire done right.

The honest version of the impact

I won't attach an invented percentage to this. What's true and defensible: a legacy vendor platform was retired and its ~20 objects / ~60 tables / 300+ fields landed in the replacement product — mapped field-by-field, reconciled before every cutover, and delivered with no disruption to live operations. The strategy was named, the risk was gated, and the vendor built to a spec I held them to.

Competencies demonstrated