Deep-diveStakeholder, Risk & Lessons Learned

The disciplines that don't show up on a Gantt chart.

Sequencing and reconciliation prove I can plan. This page is where I show the parts of the job that are harder to fake: who I managed, what I watched for, and what I got wrong.

Stakeholder management

Who I managed, and how differently

The RACI in Phase 01 tells you who was accountable for what. It doesn't tell you that a high-influence, low-interest CIO needs a different cadence than a high-interest, high-influence engineering lead — treating every stakeholder the same is how you either annoy your sponsor with detail they didn't ask for, or blindside a business owner who needed more.

Why this artifact

Without a written stakeholder register, engagement defaults to whoever emails me first. Mapping interest against influence up front is what let me protect executive time while still giving hands-on owners the detail they actually needed.

Artifact · Stakeholder registerinterest × influence
StakeholderInterestInfluenceHow I engaged them
VP, Enterprise Analytics (Sponsor)HighHighBi-weekly steering deck; direct escalation path to me, no filtering through layers
CIOMediumHighMonthly one-page executive summary — budget and risk only, no operational detail they didn't ask for
Data Engineering LeadHighHighDaily standup plus joint sprint planning — this relationship carried the technical risk of the whole program
Sales Finance SMEHighMediumWeekly working session; named as field owner so decisions had a face, not just a role
Function business owners (×8)MediumMediumMonthly function-specific update plus mandatory presence at their own UAT sign-off
QA LeadHighLowDaily standup — low formal influence, but the first person to know if the numbers were wrong

The pattern I leaned on: match cadence and detail to the quadrant, not to who's loudest. The CIO got a page, not a deck. The QA Lead got a daily seat at the table despite no line-item authority, because they were my earliest warning system on data quality.

Risk management

How I actually ran the risk register

The register itself lives in Phase 02, scoped to the technical risks that could break reconciliation. Here's the discipline behind it: how I scored, how often I reviewed, and what happened when a risk actually landed.

Why this artifact

A risk register nobody revisits is just a document I wrote once to feel prepared. Scoring by probability × impact and reviewing weekly is what forced re-scoring as reality changed — R3 moved from Medium to High once the first wave's conversion sprint ran over.

Artifact · Risk scoring modelprobability × impact
SeverityProbabilityImpactMy review cadence
High>40% likelyThreatens schedule, budget, or reconciliation accuracyWeekly, named owner reports status to me directly
Medium15–40% likelyRecoverable with effort; no scope/date impact if caught earlyWeekly, reviewed in RAID session
Low<15% likelyContained; monitoring is enoughBi-weekly spot check

The full register — including R1 through R6 and how each was mitigated — is in Phase 02: Architecture. Two risks materialized during the program: R2 (financial metric fails reconciliation) surfaced as the 6% grain-mismatch issue in Phase 03, and R3 (code conversion underestimated) is what led to the Wave 3 decoupling decision in Phase 03. Both were on the register before they happened — neither was a surprise I hadn't already named.

Lessons learned

What I'd actually do differently

The Phase 05 retrospective covers the program-level retro. These are the lessons that sit a level below that — the ones about how I personally ran things, not just what the program delivered.

Why this artifact

A lessons-learned list that only names what went well is a highlight reel, not a retro. I kept the misses in here on purpose, because the next program is where they'd actually get fixed — or repeated.

Artifact · Personal lessons learnedwhat I'd change
What happenedWhat I learnedWhat I do differently next time
SME time wasn't booked far enough ahead; it caused my one schedule slipAvailability is a resource I have to plan like headcount, not assume like goodwillReserve SME capacity per wave at planning, not at UAT
I initially ran change management as a Phase 05 activity in my head, even though the plan said day onePlans don't protect against my own instinct to prioritize the technical build first when time gets tightPut a change-management checkpoint on my own weekly review, not just the program's
Executives asked to waive the 0.003% variance for a date"Small enough to wave through" is exactly the kind of ask that erodes a zero-tolerance standard if I don't hold it the first time it's testedState the non-negotiables out loud in the charter, not just in my head, so I have something to point back to under pressure